On 17 November 2026, the third meeting of the working group convened to discuss the construction of the new Avigliana-Orbassano railway line took place at the Piedmont Region offices. The line is planned to complete the Turin-Lyon rail link and to strengthen regional rail freight transport and the logistics system. At the end of the meeting, the Region expressed greater caution about the feasibility of the project [1].
The water resources issue
The project, designed by RFI, involves a double 8-km tunnel under the Collina Morenica, a hill formed by glacial moraine west of Turin. According to what emerged during the meeting, the route would cross the area's deep aquifer, with potential interference with the springs and wells that supply over 20% of the drinking water for the city of Turin, as indicated by the Water Safety Plan drawn up by SMAT, Turin's water utility company [1].
A further risk highlighted concerns possible contamination between different water tables during excavation work, with consequences for the water supply of part of the area, starting with Turin [1].
Positions
Regional councillor (assessore) Enrico Bussalino stated that "further investigation is needed into the hydrogeological characteristics of the area crossed by the Collina Morenica, into possible interference with surface and deep aquifers, and into the effects on existing drinking-water catchments," adding that "the construction of the infrastructure cannot disregard full protection of the water resource and prior verification that the project's solutions are compatible with the characteristics of the aquifer" [1].
The regional group leader of Alleanza Verdi Sinistra (Green Left Alliance), Alice Ravinale, who has been raising the same concerns for months, commented that the Avigliana-Orbassano line is "a dead end," calling for the €827 million earmarked for the project to be redirected to public transport, in particular the €70 million still needed to complete the Cascine Vica construction site for Turin's metro Line 1 [1].
Current status
The project is funded to the amount of €828 million out of the €3 billion required overall. The environmental impact assessment procedure for the final design, launched by the Ministry of the Environment, is still under review by the VIA-VAS Technical Committee [1].
Related articles: Avigliana, Orbassano, Piedmont Region
Sources
- Tav Avigliana-Orbassano — TorinoOggi, 17 November 2026