On 17 November 2026 the Piedmont regional executive (Giunta) gave a written response, signed by the councillor responsible for (assessore) Enrico Bussalino, to a question put to the Regional Council (of Piedmont) by councillor Alice Ravinale (Alleanza Verdi Sinistra) on the state of the new Avigliana-Orbassano railway line, a section of the Torino-Lione axis [2].

The Giunta's response

In the document, the Region acknowledged that it was not possible to set a precise timetable for the approval process: the conclusion of the authorisation procedure depends on the outcome of technical assessments by the Ministry of the Environment and Energy Security, on RFI's submission of the requested design elements, and on subsequent decisions by the competent authorities. The environmental impact assessment of the final design is still under review by the VIA-VAS technical commission [2].

The overall cost of the project is estimated at around 3 billion euros, of which 827 million have been funded so far [2].

The groundwater issue

At the centre of the issue is the protection of the water resources of the Collina Morenica, a moraine hill range west of Turin. The Region stated that carrying out the project "cannot disregard the full protection of water resources and prior verification that the design solutions are compatible with the characteristics of the aquifer" [2]. In its observations sent to the Ministry, the Region asked RFI for further detail on the hydrogeological characteristics of the area crossed by the planned twin tunnel under the hill, on possible interference between surface and deep aquifers, and on the effects on existing drinking-water wells [1][2].

According to Smat (Turin's water utility) in its Water Safety Plan, more than 20% of the drinking water supplied to the city of Turin comes from the springs and wells of the Collina Morenica. The route proposed by RFI would also make several drinking-water wells unusable in the municipalities of Avigliana, Buttigliera Alta, Rosta, Rivalta di Torino and Rivoli [1].

The local authorities' positions

The issue was also discussed at a third meeting of the working table on the national section of the Torino-Lione line, convened at the Piedmont Region headquarters to discuss construction logistics, the management of excavated earth and rock, and land take. The meeting was attended by the Unione Montana Valle Susa (mountain union, Unione montana, covering the Valle Susa area) and the municipalities of Avigliana, Caselette and Sant'Ambrogio di Torino, which called for the withdrawal of the project submitted by RFI, considered technically inadequate after eleven months of procedure and already the subject of objections at the February conference of services and the subsequent meetings in June and July [1].

The president of the Unione Montana Valle Susa, Pacifico Banchieri, stated: "We are at this table and we will continue to be here, but we will never accept a blank cheque on the water we drink, on land take, on health and on the future of our citizens. RFI should withdraw the project and the funds should go where they are truly needed" [1].

Related articles: Collina Morenica, Piedmont Region, Unione Montana Valle Susa

Sources

  1. Tav Avigliana-Orbassano, acqua a rischio nella Collina Morenica — Valsusa Oggi, 17 November 2026
  2. La linea Tav Avigliana-Orbassano sul binario morto: non ci sono date certe per approvare il progetto — Valsusa Oggi, 17 November 2026

Categories

Report a mistake.