Turin Metro Line 2 Excavation Contracts Awarded
Date of the event:
On 26 November 2026 the evaluation committees of the City of Turin announced the rankings for the two tender lots covering the civil works of Metro 2, the future second line of the Turin metro. Of the nine firms or consortia that had taken part, the consortium Eteria Consorzio Stabile Scarl came first for the first lot and Webuild for the second. The overall contract is worth about one billion euros, with a further 450 million euros as an option for the extension of the Porta Nuova–Politecnico section, to be financed with government funds [1][2].
The two lots
The first lot runs from the future terminus at Torino Rebaudengo to piazzale Croce Rossa, mostly along the former railway cutting (ex trincerone), and includes the terminus itself, three above-ground stations, the underground depot, the workshop, the control room and a new urban boulevard, with an interchange at Rebaudengo with the suburban rail line (Passante ferroviario). In the ranking for this lot, behind Eteria, came Strabag, ICM, Impresa Pizzarotti and C.M.C. Ravenna [1][2].
The second lot continues from piazzale Croce Rossa to Porta Nuova, with a fully underground tunnel bored by a tunnel boring machine at a depth of about 25-30 metres, and six planned stations: Bologna, Novara, Verona, Mole/Giardini Reali, Carlo Alberto and Porta Nuova, where an interchange with Line 1 and with the railway is planned. In this ranking, behind Webuild, came Impresa Pizzarotti and Eteria [1][2].
The companies
Webuild, formerly Salini Impregilo, is engaged in Piedmont in building the Terzo Valico dei Giovi, a project that will link Turin and Genoa in under an hour by train, and is also the company in charge of the future bridge over the Strait of Messina. Eteria Consorzio Stabile was formed from a joint venture between the Caltagirone and Gavio groups and is active on several building sites in Turin, such as SMAT's water network upgrade and the Unito campus in Grugliasco, as well as outside the city, including Rome's metro Line C with the piazza Venezia station [1].
Next steps
The rankings announced on 26 November 2026 are subject to checks on the administrative documentation and verification of the operators' requirements, as required by law; only after these checks can the formal award go ahead and the contracts be signed, followed by detailed design and then the start of the first major works [1][2]. Mayor Stefano Lo Russo stated that splitting the award into two lots will allow for «a faster, more orderly and safer execution of the works» and that it provides for bonuses linked to shortening execution times and to maintenance. The president of Infra.To, Bernardino Chiaia, said that «a complex and demanding phase» is coming to a close and that the conditions are now in place to move on to the actual construction of the project [1].
Sources
- Ponte sullo Stretto e Terzo valico: chi sono Eteria e Webuild, i colossi che scaveranno la Metro 2 — La Stampa, 26 November 2026
- Metro 2 Torino, Eteria e Webuild prime nelle gare per le opere civili — Quotidiano Piemontese, 27 November 2026