Civil works tender for Turin Metro Line 2 completed

Pages linking here: 2 entries

Image from a publication by Il Torinese
From a publication by Il Torinese, 27 November 2026

On 26 November 2026 the two evaluation committees in charge of assessing the technical bids submitted for the tender to build the civil works of Line 2 of the Metropolitana di Torino completed their work [1][2].

The contract, worth a total of about 1 billion euros, with a further 450 million euros as an option for the Porta Nuova–Politecnico stretch, was split into two functional lots, distinguished by technical features and construction methods, covering the route between Rebaudengo and Porta Nuova [1].

The rankings

At the end of the evaluation committees' work and after the opening of the financial bids, the final rankings for the two lots were announced, subject to the opening of the administrative documents and the statutory checks. For the first lot: Eteria Consorzio Stabile Scarl ranked first, followed by Strabag AG, ICM S.p.A., Impresa Pizzarotti & C. S.p.A. and C.M.C. Ravenna S.p.A. For the second lot: Webuild S.p.A. ranked first, followed by Impresa Pizzarotti & C. S.p.A. and Eteria Consorzio Stabile Scarl [1][2].

Next steps

Once the administrative checks and the verification of the companies' qualifications are complete, the contracts will be formally awarded and then signed. The detailed design phase will then begin, at the end of which the first major construction sites can be opened [1][2].

Statements

Mayor Stefano Lo Russo said that, after the award of the tenders for the supply of trains and digital infrastructure and the start of the preliminary works on the trincerone, the open-air cutting that carries the mainline railway through the city, the completion of the civil-works tender procedures means the Line 2 project "becomes reality". Lo Russo explained that awarding the contract in two functional lots will allow the construction sites to proceed more quickly, in an orderly and safe manner, and that the option to extend the line to Politecnico remains dependent on further funding. The mayor pointed to early 2027 as the horizon for starting construction of the stations and tunnels [1][2].

Bernardino Chiaia, the special commissioner for Line 2, expressed satisfaction at the conclusion of the evaluation committees' work and at the quality of the proposals submitted by the participating companies, stressing that this step completes the tender procedures needed to build the new metro line [1][2].

Sources

  1. Conclusa la procedura di gara delle opere civili: il passo decisivo verso l'avvio dei cantieri di metro 2 — TorinoClick, 26 November 2026
  2. Fine della procedura di gara delle opere civili: passo decisivo verso i cantieri di Metro 2 — Il Torinese, 27 November 2026

Similar entries

Categories

Pages linking here: 2 entries

Report a mistake.