Upgrade of machine-made snow systems in Vialattea and Bardonecchia (2026)

On 14 November 2026, the companies that run the Vialattea and Bardonecchia ski areas, in the upper Susa Valley, presented in Bardonecchia the results of a multi-year programme to upgrade their snowmaking systems, with total investments of more than 20 million euros made from 2023 to the present. The works cover pumping stations, pipelines, snow generators and inverters, and are the main new feature of the 2026/27 winter season, which opens on 5 December 2026 and closes on 11 April 2027. The stated goal of the two companies is to ensure a uniform ski area, with optimal conditions even at the lower altitudes [1].

" + "

Sestriere

" + "

In the Banchetta sector, the technological renewal of the programmed snowmaking lines has been completed, which, according to Sestrieres Spa, rounds off the multi-year project begun in previous years. The works covered piste 8, the initial stretch of the upper piste 10, the upper part of the La Blu piste and the Bimbo Bassa piste. Technological upgrade works have also been started on some stretches of the Pattemouche piste [1].

" + "

Bardonecchia

" + "

In the Bardonecchia ski area, snowmaking coverage has reached 80% of the slopes in the areas of Colomion, Les Arnauds, Melezet and Jafferau. 200 new snow generators have been installed, mainly pole and tower types, bringing the total to around 350 units and making it possible to replace mobile generators and reach areas that were previously not covered [1].

" + "

At Colomion, latest-generation generators have been installed along pistes 1 upper and lower, FISI 50, 5, and 2 upper and lower. At Melezet, a new system has been built along piste 27, up to the Vallon Cros amphitheatre, to improve the continuity of ski-in/ski-out links between the different areas. At Jafferau, a new system has been built to serve the Plateau piste and the Ban starting area, with the aim of allowing the piste to open even with light snow cover and making it easier to access the Ban chairlift at the start and end of the season [1].

" + "

Water infrastructure

" + "

As part of the plan, the pumping stations have been upgraded, including two new stations completely rebuilt and upgraded in the Jafferau area, which increase the water flow of the systems and their water distribution capacity. The design of two artificial reservoirs has also been completed, one of which was created by enlarging an existing reservoir [1].

Sources

  1. Sci, Vialattea e Bardonecchia potenziano la neve programmata: spesi 20 milioni in 3 anni — Valsusa Oggi, 16 November 2026