Remediation Plan for the Former Ecolibarna Site in Serravalle Scrivia (2026)
Date of the event:
On 24 November 2026, the Piedmont Region gave the green light to a plan worth about 3.3 million euros for the remediation and safety work on the former Ecolibarna site in Serravalle Scrivia, in the Province of Alessandria. The measure updates an agreement dating back to 2015 and will be formalised through an accord to be signed by the Region, the Ministry of the Environment, the Province of Alessandria and the City of Serravalle Scrivia. The programme covers the former plant, the contaminated groundwater and environmental monitoring of the site, which is classified as a site of national interest (a category reserved for the most environmentally critical contaminated areas) [1].
The planned works
Operational management of the works is entrusted to the Province of Alessandria. About 2.1 million euros are allocated to the remediation and safety work on the former plant and on the groundwater in the surrounding areas, with particular attention to the Fabbricone area, a sector of the former industrial site. A further 1.2 million euros are earmarked for environmental monitoring of the site, from the former plant down to the Scrivia stream, and for the management of existing facilities, with technical support from Arpa Piemonte [1].
The funding includes 2.89 million euros in state funds already available to the Region and over 418,000 euros made available by the Province of Alessandria. The plan's timetable extends to 31 December 2029: the regional green light coincides neither with the signing of the accord between the bodies involved nor with the completion of the remediation [1].
Next steps
After regional approval, the accord between the bodies involved still has to be signed. According to city councillor Anna Massone, ministerial approval is expected by the end of 2026; after review by the Court of Auditors, the body overseeing the legality of public spending, the Province of Alessandria could award, in January 2027, the contracts for monitoring and for the study of the works, barring any changes [1].
Massone indicated that the new technical studies will also serve to quantify the resources still needed to complete the operations. The Piedmont Region also intends to ask the Ministry of the Environment for further funding to complete the remediation, separate from that already provided for in the plan approved on 24 November 2026 [1].
Sources
- Ex Ecolibarna a Serravalle, via libera regionale al piano di bonifica da 3,3 milioni — Quotidiano Piemontese, 26 November 2026